See more news releases in: Construction & Building, Mining & Metals, Earnings Forecasts & Projections, Sales Reports
Capstone Completed Pre-feasibility Study on Phase IV Expansion of Minto Copper-Gold Mine
- Study Extends Mine Life, Sustains Higher Production and Identifies Focus for Phase V Expansion
Capstone Mining Corporation (TSX:CS) today reported the results of a
pre-feasibility study for the Phase IV expansion ("Phase IV PFS") of its high
grade
The Phase IV PFS also discusses two possible options for further increases in production and/or increases in mine life and mineral reserves: (1) a possible further increase in mill capacity to 7,500 tpd of throughput, focused on open pit mining of mineral resources outside of the current proposed open pits, and (2) the possible development of a 1,000-2,000 tpd underground mine to provide higher grade feed relatively earlier in the mine life than an expanded open pit operation. On preliminary analysis, the underground option appears to have a more attractive investment profile. As a result, the underground option will be prioritized in 2010, offering the potential for higher production than outlined in the Phase IV PFS.
"This Phase IV pre-feasibility study represents another significant
milestone in the development of the Minto Mine," said
Phase IV PFS Highlights
Brief highlights of the Phase IV PFS are summarized below, while
additional detail follows:
- Increase in mill throughput to 4,100 tonnes per operating day,
resulting in a sustained 1.37 million tonnes of ore per year
(3,750tpd after allowances for maintenance and availability).
- Proven and probable mineral reserves increased to 10.9 million tonnes
grading 1.64% copper, 0.64 g/t gold, and 5.9 g/t silver, for a
contained 395 million lbs of copper, 224,000 oz of gold, and
2.0 million oz of silver.
- Mine life extended to 2018 with an average of 45 million pounds of
copper production per year, with additional upside opportunities
identified, as discussed below.
- Life-of-mine capital cost of C$48.2 million, primarily based on an
assumption of conversion to self mining, which decision will be
subject to a cost-benefit analysis vs. remaining with contract
mining.
- Life-of-mine cash costs of US$1.34/lb of copper, after by-product
credits (with gold at US$300/oz and silver at US$3.90/oz, as per the
agreement with Silver Wheaton).
- Net present value, at a constant US$2.25/lb copper price for unhedged
production and a 7.5% discount rate, of C$199 million before tax and
C$160 million after tax, which amounts increase to C$291 million
before tax and C$218 million after tax at a flat US$2.60/lb copper
price for unhedged production, and to C$395 million before tax and
C$281 million after tax at a flat US$3.00/lb copper price for
unhedged production.
- Important opportunities identified for incremental higher grade
production relatively early in the mine life from underground mineral
resources not within the current Phase IV pits or the current mineral
reserve.
- A C$20 million allowance has been made in the cash flow model for
post-closure abandonment and reclamation.
Phase IV Pre-feasibility Study
The Phase IV Pre-feasibility Study was undertaken by SRK Consulting
(
Mineral Resources
Updated mineral resources were estimated for each of the Area 2/118, Ridgetop and Minto North deposits. The mineral resource estimates are summarized below and are broken out by deposit at the end of this release.
Combined Mineral Resource Estimate at 0.5% Cu Cut-off for
---------------------------------------------------------
Area 2/118, Ridgetop, and Minto North Deposits(x)
-------------------------------------------------
(inclusive of reserves)(x)
--------------------------
-------------------------------------------------------------------------
Contained Contained Contained
Copper Gold Silver
Classifi- Tonnes Copper Gold Silver (000s (000s (000s
cation (000's)(x) (%) (g/t) (g/t) lbs)(x) oz)(x) oz)(x)
-------------------------------------------------------------------------
Measured
(M) 10,348 1.37 0.55 4.57 311,887 183 1,519
-------------------------------------------------------------------------
Indicated
(I) 13,920 0.94 0.30 3.39 287,179 136 1,519
-------------------------------------------------------------------------
Sub-total
(M+I)(xx) 24,267 1.12 0.41 3.89 599,066 319 3,038
-------------------------------------------------------------------------
Additional
Inferred 5,827 0.91 0.25 2.93 116,520 46 548
-------------------------------------------------------------------------
(x) This table excludes the remaining Minto Main Deposit mineral
resource
(xx) Totals may not add exactly due to rounding
The mineral resource estimate in the Area 2/118 and Ridgetop deposits was
completed by Dr.
Mineral Reserves
The Area 2/118, Ridgetop and Minto North ("Phase IV") deposits are
proposed to be developed as open pits following completion of mining in the
Minto Main deposit. The planning for this pre-feasibility study assumes a
start date of
Based on a start date of
Minto - Mineral Reserves Estimate by Deposit and Class for
----------------------------------------------------------
Main/Phase IV (including stockpiles)(x)
---------------------------------------
-------------------------------------------------------------------------
Cut-
off Diluted grade Contained Metal
Grade ----------------------------------------
(% Sil- Copper
Reserve Tonnes Copper Copper Gold ver (millions Gold Silver
Deposit Class ('000s) equiv) (%) (g/t) (g/t) lb) (oz) (oz)
-------------------------------------------------------------------------
Minto Proven 3,920 0.62 1.64 0.58 6.51 142 72 820
Main Probable 206 0.62 1.20 0.45 5.25 5 3 35
pit -----------------------------------------------------------------
Sub-total 4,126 0.62 1.62 0.57 6.45 147 75 855
-------------------------------------------------------------------------
Minto Proven 1,346 0.55 2.50 1.37 9.04 74 59 391
North Probable 3 0.55 2.91 1.07 13.11 0 0 1
Pit -----------------------------------------------------------------
Sub-total 1,349 0.55 2.50 1.37 9.05 74 60 393
-------------------------------------------------------------------------
Ridge- Proven 802 0.58 1.17 0.31 2.33 21 8 60
top Probable 522 0.58 1.39 0.50 4.90 16 8 82
Pit -----------------------------------------------------------------
Sub-total 1,324 0.58 1.26 0.38 3.34 37 16 142
-------------------------------------------------------------------------
Area Proven 3,707 0.56 1.56 0.59 5.36 127 71 639
2/118 Probable 387 0.56 1.09 0.19 2.79 9 2 35
Pit -----------------------------------------------------------------
Sub-total 4,094 0.56 1.51 0.56 5.12 137 73 674
-------------------------------------------------------------------------
Total Proven 9,775 0.58 1.69 0.67 6.08 364 211 1,911
Probable 1,118 0.58 1.25 0.38 4.26 31 14 153
-----------------------------------------------------------------
Total 10,893 0.58 1.64 0.64 5.89 395 224 2,064
-------------------------------------------------------------------------
(x) Totals may not add exactly due to rounding
The life-of-mine ("LOM") plan focuses on the mining and milling high-grade ore first, with lower grade material stockpiled for blending and processing later in the mine life. This is a strategy MintoEx has successfully employed since production commenced, based on repeated exploration success that has supported successive deferrals in the timing of the processing of this lower grade material as additional higher grade mineralization is discovered, defined and advanced to reserve status.
Open Pit Mining Production Schedule
The post-2009 mining sequence was divided into eight stages. The first stage sees the completion of mining in the Main pit followed by Minto North, the two stages in Ridgetop, Area 118 and finally three stages in Area 2. The stages were designed to provide the required ore per period, to maximize grade and defer stripping waste as long as possible.
Life-Of-Mine Open Pit Production Schedule (excluding existing stockpiles)
-------------------------------------------------------------------------
-------------------------------------------------------------------------
Year
------------------------------------------------------------
2010 2011 2012 2013 2014 2015 2016 2017 2018
Para- -----------------------------------------------------
meter Units Total Main pit Phase IV Pits
-------------------------------------------------------------------------
Mining
Ore Mt 10.0 2.0 1.3 0.3 1.4 1.2 1.4 1.3 1.1 -
Over-
burden Mt 16.9 4.9 3.4 2.3 1.2 1.6 1.0 1.9 0.7
Waste
Rock Mt 53.5 3.3 3.0 7.1 6.0 8.6 7.9 9.7 8.0
-------------------------------------------------------------------------
Total
Waste Mt 70.4 8.2 6.3 9.4 7.2 10.2 8.9 11.6 8.6 -
-------------------------------------------------------------------------
Total
Mat-
erial Mt 80.4 10.2 7.6 9.7 8.6 11.4 10.3 12.9 9.8 -
-------------------------------------------------------------------------
Strip Waste:
ratio Ore t 7.0 4.1 5.0 33.2 5.1 8.6 6.3 8.7 7.6 -
Daily
produ- 000s
ction t/day 27.5 27.8 20.9 26.4 23.5 31.1 28.3 35.3 26.8 -
Mined
Copper
grade % 1.66 1.71 1.59 1.20 2.43 1.28 1.42 1.42 1.80 -
Mined
Gold
grade g/t 0.65 0.52 0.67 0.50 1.24 0.43 0.51 0.51 0.73 -
Mined
Silver
grade g/t 5.93 7.04 6.23 2.27 8.71 3.76 5.23 4.48 6.00 -
-------------------------------------------------------------------------
Mil-
Mined lions
Copper lbs 367 74 45 7 75 33 44 42 45 -
Mined 000s
Gold oz 210 33 28 5 56 16 23 22 27 -
Mined 000s
Silver oz 1,912 447 257 21 394 143 238 192 221 -
-------------------------------------------------------------------------
Processing
Based on recent operating experience at the Minto Mine, combined with metallurgical and comminution test work undertaken on each of the deposits forming the Phase IV pits, recoveries and processing characteristics were determined for each deposit, resulting in the mill processing profile tabulated below.
Life-Of-Mine Mill Processing Schedule
-------------------------------------
-------------------------------------------------------------------------
Year
------------------------------------------------------------
2010 2011 2012 2013 2014 2015 2016 2017 2018
Para- -----------------------------------------------------
meter Units Total Main pit Phase IV Pits
-------------------------------------------------------------------------
Pro-
cessing
Process-
ed Ore Mt 10.9 1.2 1.4 1.4 1.4 1.4 1.4 1.4 1.4 0.1
Process
rate tpd 3,704 3,334 3,750 3,750 3,750 3,750 3,750 3,750 3,750 3,750
Process-
ed Cu
grade % 1.64 2.33 1.68 1.10 2.47 1.22 1.44 1.40 1.64 0.81
Process-
ed Au
grade g/t 0.64 0.80 0.67 0.35 1.27 0.40 0.52 0.50 0.65 0.25
Process-
ed Ag
grade g/t 5.89 9.84 6.48 3.64 8.88 3.66 5.32 4.44 5.52 2.67
-------------------------------------------------------------------------
Recovery
Copper % 92.8 94.0 94.0 93.6 92.0 92.3 92.0 92.0 92.4 92.0
Gold % 73.8 80.0 80.0 77.9 70.0 71.3 70.0 70.2 71.8 70.0
Silver % 81.3 86.7 86.7 84.9 78.0 79.1 78.0 78.2 79.6 78.0
-------------------------------------------------------------------------
Metal in Concentrates
Mil-
lions
Copper lbs 366 59 48 31 69 34 40 39 46 1
000s
Gold oz 164.8 25.0 23.5 12.2 39.2 12.5 16.0 15.6 20.4 0.5
000s
Silver oz 1,685 334 247 136 305 127 183 153 193 6
-------------------------------------------------------------------------
As noted in the Phase IV PFS, the mining schedule is not fully optimized and will be reworked to smooth out production, particularly in the 2012-2014 period. Nor does this production profile include any contribution from possible underground production, which could result in higher grade underground feed displacing lower grade open pit feed, which would be deferred into future years (see below).
Production Opportunities
In order to assess the possible opportunity for larger scale open pits and their potential impact on future permitting requirements, a preliminary study was conducted where an optimistic copper price and lower operating costs were used to understand these potential pit limits. Although the large scale pits provide the potential for more tonnage through the mill (due to the lower operating costs and higher copper prices assumed), they do so at a reduced copper grades and also would require significant increases in waste dump capacities, as well as tailings storage requirements. It should be noted that this large open pit scenario is preliminary in nature and only serves as a rough indication of potential pit size.
Exploration on the
Both scenarios will undergo continued evaluation, with the underground potential being the preferred option due to the potential for the extraction and processing of relatively higher copper grades sooner, with lower capital than the large pit scenario.
Capital Cost Estimate
Life-of-mine capital costs are estimated at
Phase IV PFS Capital Cost Estimate
----------------------------------
--------------------------------------
Area C$ millions
--------------------------------------
Plant expansion 9.1
--------------------------------------
Open pit mining equipment 33.7
--------------------------------------
Sub-total 42.8
--------------------------------------
Sustaining Capital 5.4
--------------------------------------
Life-of-mine capital 48.2
--------------------------------------
The method of funding the possible acquisition of open pit mining
equipment, which could be by cash, capital lease or other method, will be
evaluated once a decision to proceed with self-mining has been made.
Alternatively, contract mining could continue, if contractors can achieve the
objectives set out under 'Operating Cost' section below, eliminating the need
for the open pit mining capital noted above.
Operating Cost Estimate
The direct operating costs for the Phase IV PFS were estimated using historical operating data from the Minto Mine and various planned optimizations related to the Phase IV expansion.
Phase IV PFS Operating Cost Estimate
------------------------------------
------------------------------------------------------------
Area C$/t
------------------------------------------------------------
Mining ($/t material mined) 2.31
------------------------------------------------------------
------------------------------------------------------------
Mining ($/t milled) 17.02
------------------------------------------------------------
Processing ($/t milled) 13.90
------------------------------------------------------------
General, administration, camp, royalties ($/t milled) 11.94
------------------------------------------------------------
Total ($/t milled) 42.86
------------------------------------------------------------
This equates to a life-of-mine average total cash cost, after selling
costs and net of by-product credits, of
Economics
SRK reports that the estimated economic benefit of mining the Minto Phase IV deposits is sufficient to take the Phase IV expansion project to the next level. While more detailed work will be required to optimize the project, there is adequate economic justification for MintoEx to proceed with further work and, in particular, the application for licence and permit amendments from the Yukon Government.
The table below shows the comparison of Phase IV PFS Base Case (at a flat
Comparison of Phase IV Base and Alternate Cases
-----------------------------------------------
-------------------------------------------------------------------------
Phase IV Phase IV Phase IV
PFS Base PFS PFS
Item Unit Case Case 2 Case 3
-------------------------------------------------------------------------
Waste mined (millions) tonnes 70.4 70.4 70.4
-------------------------------------------------------------------------
Ore mined (millions) tonnes 10.0 10.0 10.0
-------------------------------------------------------------------------
Total mined (millions) tonnes 80.4 80.4 80.4
-------------------------------------------------------------------------
Strip ratio (waste: ore) W:O 7.0 7.0 7.0
-------------------------------------------------------------------------
Mill Feed(x) Mt 10.9 10.9 10.9
-------------------------------------------------------------------------
Copper mill head grade % Cu 1.64% 1.64% 1.64%
-------------------------------------------------------------------------
Gold mill head grade g/t Au 0.64 0.64 0.64
-------------------------------------------------------------------------
Silver mill head grade g/t Ag 5.9 5.9 5.9
-------------------------------------------------------------------------
Copper in concentrates
(millions) lb 366 366 366
-------------------------------------------------------------------------
Gold in concentrates (000s) oz 166 166 166
-------------------------------------------------------------------------
Silver in concentrates (000s) oz 1,685 1,685 1,685
-------------------------------------------------------------------------
Concentrate Grade % Cu 40% 40% 40%
-------------------------------------------------------------------------
Copper Price Unhedged
production, flat) US$/lb $2.25 $2.60 $3.00
-------------------------------------------------------------------------
Copper Price (LOM average,
including hedging) US$/lb US$2.25 US$2.55 US$2.90
-------------------------------------------------------------------------
Gold price (net received from
Silver Wheaton) US$/oz $300.00 $300.00 $300.00
-------------------------------------------------------------------------
Silver price (net received
from Silver Wheaton) US$/oz $3.90 $3.90 $3.90
-------------------------------------------------------------------------
Exchange rate US$/C$ $0.91 $0.91 $0.91
-------------------------------------------------------------------------
NSR C$/t milled $75 $86 $99
-------------------------------------------------------------------------
Unit Mining Costs C$/t mined $2.31 $2.31 $2.31
-------------------------------------------------------------------------
Unit Total OPEX (incl.
royalties) C$/t milled $42.86 $42.92 $42.98
-------------------------------------------------------------------------
Unit On-site OPEX (inc. US$/lb Cu
royalties) payable $1.20 $1.20 $1.20
-------------------------------------------------------------------------
US$/lb Cu
Unit Off-site OPEX payable $0.29 $0.29 $0.29
-------------------------------------------------------------------------
US$/lb Cu
Unit By-product Credit payable $0.15 $0.15 $0.15
-------------------------------------------------------------------------
Unit OPEX net by-product US$/lb Cu
credits payable $1.34 $1.34 $1.34
-------------------------------------------------------------------------
Total Capital (initial,
sustaining) C$ millions $48 $48 $48
-------------------------------------------------------------------------
Allowance for closure costs C$ millions $20 $20 $20
-------------------------------------------------------------------------
NPV7.5% pre-tax C$ millions $199 $291 $395
-------------------------------------------------------------------------
NPV7.5% after tax C$ millions $160 $218 $281
-------------------------------------------------------------------------
(x) Note: Mill Feed includes Ore Stockpile
Base case sensitivity analyses were run for copper grade, copper price,
capital expense ("CAPEX"), and operating expense ("OPEX"). Each variable was
changed from -20% to +20% of the base case value. Each variable was changed
independently of the other variables so there is no compounding effect of
multiple variable modifications. The results show the project is most
sensitive to copper grade followed closely by copper prices. Normally grade
and metal price effects are equal but in
For Case 1 Sensitivity of Project Economics, please click:
http://files.newswire.ca/842/CapstoneMiningCase1.doc
Permitting & Reclamation
In order to implement the life-of-mine plan set out in the Phase IV PFS,
amendments will be required to the current operating permits and licences at
the Minto Mine for production in 2012 and beyond. With the Phase IV PFS as a
guide, MintoEx has commenced the process of preparing an application for such
amendments, which application it intends to file with the
In the financial model,
Risks & Opportunities
The major risk areas identified in this study are:
1. Timing and approval of permit revisions, which could delay access to
new mining areas if not granted in time to allow stripping of Minto
North in 2012;
2. Exchange rates, metal prices and external influences;
3. Grade control, given the relatively narrower mineralized horizons in
the Phase IV pits as compared to the Minto Main pit.
The most important opportunities to improve the project are:
1. Optimization of mine plan to smooth out the production profile and
optimize stripping;
2. Underground production potential, bringing currently defined ex-pit
high grade feed to the mill relatively early in the mine life. A
conceptual level review was completed that involves underground
extraction of higher grade ore, eliminating the need for further
plant expansions and allowing processing of higher grade ore sooner
than in an expanded open pit scenario:
3. Conversion of current inferred mineral resources within existing
Phase IV pit outlines to higher classifications, increasing the
mineral reserve and reducing strip ratios:
4. Conversion of current higher grade inferred mineral resources
outside the existing Phase IV pit outlines to higher
classifications, possibly resulting in increased mineral reserves;
and
5. Discovery of new mineral resources and mineral reserves.
Underground Mining Opportunity
As part of the review of the mineral resources for the Phase IV PFS, options for extracting deeper portions of the resources that remain outside of the open pit limits were examined. One consideration was the potential for underground extraction of mineral resources, particularly in the Area 2/118 areas, and the potential of other deeper, but higher grade discoveries such as Minto East and Copper Keel.
Potentially Underground Mineable Mineralization in Area 118 and Area 2
----------------------------------------------------------------------
(Using Measured and Indicated Mineral Resources only)
-------------------------------------------------------------------------
Diluted Grade Thickness
(10%) (Min. 3m)
-------------------------------------
Cut-off In situ Max Average %
Value Tonnes Cu Au Ag Thickness Thickness Ben-
Deposit ($/t NSR) (000s t) (%) (g/t) (g/t) (m) (m) ching
-------------------------------------------------------------------------
60 1,340 1.98 0.79 8.3 15.9 7.1 40
Area 118 75 783 2.34 0.96 10.4 16.0 6.9 38
90 515 2.63 1.10 12.3 13.5 6.9 37
-------------------------------------------------------------------------
60 1,814 1.83 0.75 6.0 33.0 11.2 64
Area 2(x) 75 1,186 2.04 0.87 6.8 30.0 8.8 53
90 555 2.34 1.07 7.8 27.5 7.3 42
-------------------------------------------------------------------------
(x) Includes some mineralization currently in the Area 2 mine plan.
Based on geologic and geotechnical information, mining conditions in
these areas appear to be good and may be able to support high extraction,
relatively low cost, room and pillar mining. In order to access both the Area
2 and Area 118 mineralization, a 1,650m long, 5m by 5m decline at -15% has
been considered, with additional development required to access
mineralization and provide ventilation, with capital costs for such
development estimated at
If a
Large Pit Scenario
The work leading up to the Phase IV PFS also included the preliminary examination of the possibility of a further increase in mill capacity, to 7,500 tpd, concurrent with expanded mining capacity, resulting in a reduction in unit operating costs as efficiencies of scale come to bear. A reduction in unit operating costs could result in conversion of mineral resources currently outside the Phase IV pits into mineral reserves, particularly at higher metal prices, justifying the higher throughput. However, such a scenario involves more capital investment up front than the underground option discussed above, and reaches the highest grades toward the end of the mine life, and would thus appear to result in a less attractive investment scenario than the underground option, except at high metal prices over the entire mine life. MintoEx therefore intends to focus on evaluating the underground option for its Phase V of the Minto Mine.
Mineral Resource Estimation
In the opinion of SRK, the block model mineral resource estimate and mineral resource classification reported herein are a reasonable representation of the global mineral resources at Area 2/118, Ridgetop, and Minto North deposits at the current level of sampling. The mineral resources presented herein have been estimated in conformity with generally accepted CIM "Estimation of Mineral Resource and Mineral Reserves Best Practices" guidelines and are reported in accordance with Canadian Securities Administrators' National Instrument 43-101. Mineral resources are not mineral reserves and do not have demonstrated economic viability. The estimated mineral resources have been used in the preliminary feasibility study described in this news release.
The database used to estimate the Area 2/118 and Ridgetop deposits was audited by SRK and the mineralization boundaries were modelled by SRK based on lithological and structural interpretations. Kirkham Geosystems audited the Minto North database and modelled mineralization boundaries. SRK and Kirkham Geosystems are of the opinion that the current drilling information is sufficiently reliable to interpret with confidence the boundaries of the mineralized domains and that the assaying data is sufficiently reliable to support estimating mineral resources in respect of the mineral resource estimates they are responsible for.
The "reasonable prospects for economic extraction" requirement for a mineral resource generally implies that the quantity and grade estimates meet certain economic thresholds, and that the mineral resources are reported at an appropriate cut-off grade taking into account extraction scenarios and processing recoveries. In order to meet this requirement, SRK and Kirkham Geosystems consider that the Area 2/118, Ridgetop, and Minto North deposits are amenable for open pit extraction.
In order to constrain the overall mineral resource envelope to
demonstrate reasonable prospects for economic extraction, for the Area 2/118
and Ridgetop deposits, the mineral resources are based on a combined
processing and G&A cost of
The open pit resource is constrained by an optimized Whittle shell based on the NSR model, overall slope angles of 50 degrees and the site operating costs noted above. At Minto North, global resources have been reported.
Technical Report
----------------
A technical report summarizing the information in the Phase IV PFS will be filed on SEDAR within approximately one week.
The TSX does not accept any responsibility for the adequacy or accuracy of this press release.
Quality Assurance
The technical information in this news release has been prepared in
accordance with Canadian regulatory requirements set out in National
Instrument 43-101 and reviewed by
The following SRK employees are the Qualified Persons ("QP") under
National Instrument 43-101 responsible for this project:
The analytical method for the copper and silver analyses is aqua regia
digestion of the samples followed by atomic absorption spectroscopy. Gold is
analysed by fire assay fusion with atomic absorption spectroscopy finish for
gold. Analyses are carried out by ALS CHEMEX in
Forward-Looking Statements
This document may contain "forward-looking information" within the meaning of Canadian securities legislation and "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 (collectively, "forward-looking statements"). These forward-looking statements are made as of the date of this document and Capstone Mining Corp. (the "Company") does not intend, and does not assume any obligation, to update these forward-looking statements.
Forward-looking statements relate to future events or future performance and reflect Company management's expectations or beliefs regarding future events and include, but are not limited to, statements with respect to the estimation of mineral reserves and mineral resources, the realization of mineral reserve estimates, the timing and amount of estimated future production, costs of production, capital expenditures, success of mining operations, environmental risks, unanticipated reclamation expenses, title disputes or claims and limitations on insurance coverage. In certain cases, forward-looking statements can be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "perhaps", "would", "might" or "will be taken", "occur" or "be achieved" or the negative of these terms or comparable terminology. In this news release, forward-looking statements can be identified by the use of words (or variations of words) such as "resulting", "further" "planning", "planned", "could", "will", "proposed", "would", "scenario", "may", "intends", "opportunities", "potential", and relate to the Company's expectations with respect to the expansion of the Minto Mine based on the Phase IV PFS. By their very nature forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors can include, among others, risks related to actual results of current exploration activities; changes in project parameters as plans continue to be refined; future prices of mineral resources; possible variations in ore reserves, grade or recovery rates; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing or in the completion of development or construction activities; as well as those factors detailed from time to time in the Company's interim and annual financial statements and management's discussion and analysis of those statements, all of which are filed and available for review on SEDAR at http://www.sedar.com. Specific risks identified in this news release are risks related to the timing and receipt of permit amendments required to implement the mine expansion; exchange rates, metal prices and external influences; and grade control in mining the Phase IV pits. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward- looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.
Accordingly, readers should not place undue reliance on forward-looking
statements.
Mineral Resource Estimates for Individual Deposits
--------------------------------------------------
(excluding Main Deposit)
------------------------
Mineral Resource Statement at 0.5% Cu Cut-off for the Area 2/118
Deposit, SRK Consulting June 9, 2009
-------------------------------------------------------------------------
Contained Contained Contained
Copper Gold Silver
Classifi- Tonnes Copper Gold Silver (000s (000s (000s
cation (Kt)(x) (%) (g/t) (g/t) lbs)(x) oz)(x) oz)(x)
-------------------------------------------------------------------------
Measured
(M) 6,936 1.25 0.47 4.3 190,638 104 956
-------------------------------------------------------------------------
Indicated
(I) 11,301 0.92 0.29 3.4 230,198 106 1,220
-------------------------------------------------------------------------
Sub-total
(M+I)(xx) 18,237 1.05 0.36 3.7 420,836 210 2,176
-------------------------------------------------------------------------
Inferred 5,116 0.91 0.24 3.0 102,420 40 492
-------------------------------------------------------------------------
(x) Rounded to nearest thousand
(xx) Totals may not add exactly due to rounding
Mineral Resource Statement at 0.5% Cu Cut-off for the
Ridgetop Deposit, SRK Consulting June 9, 2009
-------------------------------------------------------------------------
Contained Contained Contained
Copper Gold Silver
Classifi- Tonnes Copper Gold Silver (000s (000s (000s
cation (000's)(x) (%) (g/t) (g/t) lbs)(x) oz)(x) oz)(x)
-------------------------------------------------------------------------
Measured
(M) 1,568 0.98 0.26 2.1 33,719 13 107
-------------------------------------------------------------------------
Indicated
(I) 2,355 0.98 0.33 3.3 50,926 25 250
-------------------------------------------------------------------------
Sub-total
(M+I)(xx) 3,923 0.98 0.30 2.8 84,645 38 357
-------------------------------------------------------------------------
Inferred 686 0.90 0.26 2.4 13,644 6 53
-------------------------------------------------------------------------
(x) Rounded to nearest thousand
(xx) Totals may not add exactly due to rounding
Mineral Resource Statement at 0.5% Cu Cut-off for the Minto North
Deposit, Kirkham Geosystems, Dec. 1, 2009
------------------------------------------------------------------------
Contained Contained Contained
Copper Gold Silver
Classifi- Tonnes Copper Gold Silver (000s (000s (000s
cation (000's)(x) (%) (g/t) (g/t) lbs)(x) oz)(x) oz)(x)
------------------------------------------------------------------------
Measured
(M) 1,844 2.15 1.11 7.7 87,530 66 456
Indicated
(I) 264 1.04 0.6 5.8 6,055 5 49
-------------------------------------------------------------------------
Sub-total
(M+I)(xx) 2,108 2.01 1.04 7.5 93,585 71 505
-------------------------------------------------------------------------
Additional
Inferred 25 0.84 0.40 4.4 457 0 3
-------------------------------------------------------------------------
(x) Rounded to nearest thousand
(xx) Totals may not add exactly due to rounding
For further information: about Capstone, please contact:
SOURCE Capstone Mining Corp.
Back to top
Custom Packages
Browse our custom packages or build your own to meet your unique communications needs.
PR Newswire Membership
Fill out a PR Newswire membership form or contact us at (888) 776-0942.
Learn about PR Newswire services
Request more information about PR Newswire products and services or call us at (888) 776-0942.
Featured Video
More in These Categories
Journalists and Bloggers
![]()
Visit PR Newswire for Journalists for releases, photos, ProfNet experts, and customized feeds just for Media.
View and download archived video content distributed by MultiVu on The Digital Center.
Free Investing Newsletter from Investor Uprising!
Learn to navigate the world's financial system and profit from leading companies.
Register for Investor Uprising, the people's investment site, for a free weekly newsletter, information, education and premium research including our latest IU Confidential Report - "All The Glitters: The Ultimate Gold Report".
