2014

Pacific Booker Minerals Inc. Announces Power Availability

    VANCOUVER, British Columbia, June 12 /PRNewswire-FirstCall/ -- The
 Company is pleased to announce that it has confirmed the availability of
 power from the former Bell mine electrical facility located 22 km from the
 Morrison project site. The 138 kV service, which was extended to the Bell
 Mine in 1971, is now energized at 25 kV and can be re-energized to its
 design voltage. A new 24.7 km 138 kV overhead line will be constructed from
 the former Bell mine site to the proposed Morrison mine site substation. A
 transmission system Load Interconnection Study was also completed by BC
 Hydro for the proposed new load.
 
     To view information regarding Pacific Booker Minerals Inc. (AMEX:   PBM;
 CDNX: BKM.V), please visit our website home page and reports section at
 http://www.pacificbooker.com.
 
     Contact: Gregory R. Anderson
 
 
President & CEO 1-800-234-3680

SOURCE Pacific Booker Minerals Inc.

Custom Packages

Browse our custom packages or build your own to meet your unique communications needs.

Start today.

 

PR Newswire Membership

Fill out a PR Newswire membership form or contact us at (888) 776-0942.

Learn about PR Newswire services

Request more information about PR Newswire products and services or call us at (888) 776-0942.